Skip to main content
Department for Infrastructure Department for Infrastructure An Roinn Bonneagair Depairtment fur Infrastructure

Main navigation

  • Home
  • Topics
  • Publications
  • Consultations
  • Contact

Translation help

Translate this page

Select a language

  • Arabic — عربي
  • Chinese (Simplified) — 中文简体
  • Chinese (Traditional) — 中文繁體
  • Dutch — Nederlands
  • Filipino — Filipino
  • French — Français
  • German — Deutsch
  • Hungarian — Magyar
  • Irish — Gaeilge
  • Italian — Italiano
  • Latvian — Latviešu
  • Lithuanian — Lietuvių kalba
  • Polish — Polski
  • Portuguese — Português
  • Romanian — Română
  • Russian — Русский
  • Slovak — Slovenčina
  • Spanish — Español
  • Ukrainian — Українська
  • Mid Ulster Council Report 2026 - Major Projects and Active Travel

    Topics:
    • Roads, 
    • Council Reports

    This page provides details specific to Mid-Ulster Council area for 2026.

    Project Lifecycle

    Strategic Road Improvements

    Major road improvements - inception to construction RSPPG E030v5 | Department for Infrastructure (infrastructure-ni.gov.uk)

    Scheme Name 1 – A5 Western Transport Corridor (A5WTC)

    TABLE 60: Scheme 1 details

    District Council area(s)Derry City and Strabane; Fermanagh and Omagh; Mid-Ulster.
    LocationNew Buildings to border south of Aughnacloy
    Scheme descriptionProvision of new off-line dual carriageway
    Scheme length85 km
    Scheme estimated cost£2.1 bn
    Scheme websiteA5wtc.com
    Any related schemes?ROI Links - N14/N15 upgrade schemes at Lifford and N2 upgrade schemes south of the border in Monaghan. 
    Current stage The A5 Western Transport Corridor (A5WTC) project remains at the statutory procedure stage.
    Current position

    Previously Authorised Section ( Section 2 and Section 3 Phase 1 B Sion Mills to Ballygawley)

    The Court of Appeal found in favour of the Department on all grounds on 6 October 2026. Any party to the litigation may still seek leave to appeal this decision.  While the Department was successful, the legal position remains unchanged until the Court makes the formal order giving effect to its judgment. As the wording of that order may affect the next steps, the Department will await its receipt before taking any substantive action. However, in the background the Department is continuing to progress the work required to enable delivery of this important strategic route at the earliest opportunity. This will involve completing the remaining checks and approvals as well as getting agreement on costs with the current contractors.

    Section 1 (New Buildings to Sion Mills)
    Work continues on a new Stage 2 Scheme Assessment to identify route options for Section 1. This includes assessment of the previously identified Preferred Route alongside alternative route options using updated environmental, engineering, traffic and economic information. The outcome of these assessments, together with feedback received through public engagement events, will inform the identification of a Preferred Route. Close collaboration is also ongoing with the Irish Government in relation to the adjoining TEN-T projects and with OPW in relation Lifford Flood Relief Scheme.

    Section 3 Phase 3 (Ballygawley to south of Aughnacloy)
    Work is continuing on elements of Section 3 Phase 3 that can be progressed at this stage. Close collaboration also continues with the Irish Government in relation to the adjoining N2 infrastructure projects.

    Scheme Name 2 - A29 Cookstown Bypass

    TABLE 61: Scheme 2 details

    District Council area(s)Mid-Ulster
    LocationCookstown
    Scheme descriptionProvision of a new bypass to the east of Cookstown extending from the A0029 Dungannon Road to the A0029 Moneymore Road. The scheme includes for improvements the Sandholes Link Road from Drum Road to Sandholes Road. A footway/cycleway will be provided along its entire length connecting into the existing network.
    Scheme length4 km
    Scheme estimated cost£100m
    Scheme websiteA29 Cookstown Bypass
    Current stage The draft Statutory Orders and Environmental Impact Assessment Report were published on 03 April 2024. Following the consultation period, it was agreed to hold a Public Inquiry on the scheme which commenced on 22 October 2024 and concluded on the 24 October 2024. The Inspector’s Report was received by the Department in February 2025, and the recommendations have been carefully reviewed. The Department held a Social Valve Engagement exercise in Autumn 2025 to seek the views of the community on the wider social value benefits they would like to see delivered as part of the A29 Cookstown Bypass scheme. The Outline Business Case for the scheme has been issued to the Department of Finance for approval in September 2026, with approval being aligned with the MSW Growth Deal signing in early 2027.
    Current position

    The Court's judgment on the A5 Appeal represents a significant milestone for the Department. Time will be taken to consider it in detail and its implications for the major projects to be taken forward by the Department, however, the judgment provides important legal clarity and vindicates the Department’s position throughout that it complied with the requirements of the Climate Change Act.

    The positive judgment on the A5 appeal would permit my officials to proceed with the making of the relevant Statutory Orders. The timescales for progressing to procurement and construction will depend on several factors including, the completion of statutory procedures and the availability of funding in future years.

    Active Travel

    Completed Works 2025 – 2026

    TABLE 70.1: Pedestrian Measures completed

    Number of sites Total cost
    1£100,000
    Road Number Road NameScheme DescriptionStatus
    A0045Ballynakilly Road, Coalisland at Creenagh BridgeFootway provision (in conjunction with a Carriageway realignment and Bridge Replacement scheme)Complete

    TABLE 70.2: Cycling Measures completed

    Number of sites Total cost
    3£592,000
    Road Number Road NameScheme DescriptionStatus
    A0029Dungannon Road, CookstownFootway/Cycleway provision (Phase 2) from Riverdale Drive towards Killycolp RoadComplete

    B0040

    B0161

    Moneymore Road &

    Ballyronan Road, Magherafelt

    Cycleway provision from Moneymore Road to Ballyronan Road & Meadowbank Road – Route Appraisal and Preliminary DesignOngoing
    U5147Killyfaddy Road, MagherafeltFootway/Cycleway provision – Design and Lands AcquisitionOngoing

    Planned Works 2026 – 2027

    TABLE 71.1: Pedestrian Measures planned

    Number of sites Total cost
    N/AN/A
    Road Number Road NameScheme DescriptionStatus
    N/A   

    TABLE 71.2: Cycling Measures planned

    Number of sites Total cost
    10£165,000
    Road Number Road NameScheme DescriptionStatus
    A0042Gulladuff Road, GulladuffFootway/Cycleway provision from Gulladuff Village towards Maghera – Lands AcquisitionOngoing
    A0045 Granville Road, DungannonFootway/Cycleway provision (Phase 2) from Granville Industrial Estate towards Killybracken Road – Lands AcquisitionOngoing
    B0034Killycolp Road, CookstownFootway/Cycleway provision from A29 Dungannon Road towards CAFRE Campus – Design and Lands AcquisitionOngoing

    B0040

    B0161

    Moneymore Road &

    Ballyronan Road, Magherafelt

    Cycleway provision from Moneymore Road to Ballyronan Road & Meadowbank Road –Preliminary DesignOngoing
    B0043Mullaghmore Road, DungannonFootway/Cycleway provision from Castleview Heights towards Town Boundary – Lands AcquisitionOngoing
    B0161Mountjoy Road, BrockaghFootway/Cycleway provision (in conjunction with a Network Development Carriageway Realignment scheme) – Lands AcquisitionOngoing
    B0182Deerpark Road, The CreaghFootway/Cycleway provision from Hillhead Road towards Anahorish Primary School – Lands AcquisitionOngoing
    C0051Tirkane Road, MagheraFootway provision at St Brigid’s Primary School / An Carn Centre – Lands AcquisitionOngoing
    U1027Gortgonis Road, CoalislandFootway provision from Moor Road (west) towards Coalisland Canal and (east) towards Annaghmore Road – Route Appraisal and Preliminary DesignPlanned
    U5147Killyfaddy Road, MagherafeltFootway/Cycleway provision – Design and Lands AcquisitionOngoing

    Related content

    • Derry City and Strabane Council Report - 2024
    • Derry City and Strabane Council Report - 2025
    • Derry City and Strabane Council Report 2023/2024 - Major Projects and Active Travel
    • Derry City and Strabane Council Report 2023/2024 - Network Development
    • Derry City and Strabane Council Report 2023/2024 - Network Maintenance
    • Derry City and Strabane Council Report 2023/2024 - Network Planning
    • Derry City and Strabane Council Report 2024/2025 - Major Projects and Active Travel
    • Derry City and Strabane Council Report 2024/2025 - Network Development
    • Derry City and Strabane Council Report 2024/2025 - Network Maintenance
    • Derry City and Strabane Council Report 2024/2025 - Network Planning
    • Fermanagh and Omagh Council Report - 2024
    • Fermanagh and Omagh Council Report - 2025
    • Fermanagh and Omagh Council Report 2024 - Major Projects and Active Travel
    • Fermanagh and Omagh Council Report 2024 - Network Development
    • Fermanagh and Omagh Council Report 2024 - Network Maintenance
    • Fermanagh and Omagh Council Report 2024 - Network Planning
    • Fermanagh and Omagh Council Report 2025 - Major Projects and Active Travel
    • Fermanagh and Omagh Council Report 2025 - Network Development
    • Fermanagh and Omagh Council Report 2025 - Network Maintenance
    • Fermanagh and Omagh Council Report 2025 - Network Planning
    • Fermanagh and Omagh Council Report 2026 - Major Projects and Active Travel
    • Fermanagh and Omagh Council Report 2026 - Network Development
    • Fermanagh and Omagh Council Report 2026 - Network Maintenance
    • Fermanagh and Omagh Council Report 2026 - Network Planning
    • List of Council Reports - 2023/24
    • Mid Ulster Council Report 2026 - Network Development
    • Mid Ulster Council Report 2026 - Network Maintenance
    • Mid Ulster Council Report 2026 - Network Planning
    • Mid-Ulster Council 2022/2023 - Major Projects and Active Travel
    • Mid-Ulster Council 2022/2023 - Network Development
    • Mid-Ulster Council 2022/2023 - Network Maintenance
    • Mid-Ulster Council 2022/2023 - Network Planning
    • Mid-Ulster Council 2023/2024 - Major Projects and Active Travel
    • Mid-Ulster Council 2023/2024 - Network Development
    • Mid-Ulster Council 2023/2024 - Network Maintenance
    • Mid-Ulster Council 2023/2024 - Network Planning
    • Mid-Ulster Council 2024/2025 - Major Projects and Active Travel
    • Mid-Ulster Council 2024/2025 - Network Development
    • Mid-Ulster Council 2024/2025 - Network Maintenance
    • Mid-Ulster Council 2024/2025 - Network Planning
    • Mid-Ulster District Council Report - 2023
    • Mid-Ulster District Council Report - 2024
    • Mid-Ulster District Council Report - 2025
    Share this page Share on Facebook (external link opens in a new window / tab) Share on X (external link opens in a new window / tab) Share by email (external link opens in a new window / tab)

    Department footer links

    • Crown copyright
    • Terms and Conditions
    • Privacy
    • Cookies
    • Accessibility
    • The Northern Ireland Executive
    • The Executive Office
    • Department of Agriculture, Environment and Rural Affairs
    • Department for Communities
    • Department for Education
    • Department for the Economy
    • Department of Finance
    • Department for Infrastructure
    • Department for Health
    • Department of Justice
    • nidirect.gov.uk — the official government website for Northern Ireland citizens