Work on a £275,000 drainage infrastructure scheme in Whiteabbey will commence on Monday 16 April 2018.
The scheme has been developed to reduce the risk of flooding to 29 properties in Whiteabbey, through the replacement of an existing inadequate and structurally defective masonry culvert.
The scheme, which will take approximately 12 weeks to complete, will involve the construction of a new precast concrete box culvert in Glenville Way, and scour protection works downstream of the Shore Road.
These works are being undertaken by Lowry Building and Civil Engineering.
Notes to editors:
1. All media queries should be directed to the Department for Infrastructure Press Office on 028 9054 0007 or email: press.office@infrastructure-ni.gov.uk. Out of office hours please contact the duty press officer via pager number 07623 974 383.
2. Follow the Department on Twitter @deptinfra and on Facebook @DepartmentforInfrastructure
Latest news
- The Northern Ireland Planning Statistics: Third Quarter 2023/24 Statistical Bulletin, has been published today 28 March 2024
- Statistical Press Release - Walking and Cycling in Northern Ireland 2022/23 report 28 March 2024
- O’Dowd advises road users to take extra care on the roads over Easter break 28 March 2024
- Flood protection refurbishment work gets underway on the River Lagan 27 March 2024